TSP NameTSP DUNSPost DatePost Time
KERN RIVER GAS TRANSMISSION COMPANY 621617372 05/30/2024 04:40:56

Notice TypePosted
Date/Time
Notice Effective
Date/Time
Notice End
Date/Time
Notice
Identifier
SubjectResponse
Date/Time
Notice
Status
Prior
Notice
Identifier
         

There are no Planned Service Outages in effect.
Notice Status Key:
1 = Initiate
2 = Supersede
3 = Terminate

 

Planned Service Outage - Maintenance Schedule


TSP NameTSP DUNSPost DatePost Time
KERN RIVER GAS TRANSMISSION COMPANY 621617372 05/30/2024 04:40:56

StatusStart DateEnd DateLocation NameCapacity
Reduction
Location
Work to be
Performed
Estimated
Operational
Capacity Dth
Estimated
Operational
Capacity
Reduction Dth
Anticipated
Impact
to Firm
Nominations
Additional Information
CompletedThu 03/07/2024Fri 05/31/2024Centennial Meter StationCentennial - SW GasLine Replacement 209,000 209,000NoThe Centennial meter station will be out of service for the duration of the project.
 Mon 05/27/2024Tue 06/11/2024Riverton Meter StationRiverton - Questar GasStrength TestTBDTBDNoThe Riverton meter station will be out of service for the duration of the project.
 Wed 10/02/2024Thu 10/10/2024Muddy Creek "A" Compressor StationMuddy CreekUnit #3 Controls UpgradeTBDTBDNoUnit one and two will be available for the duration of the unit #3 controls upgrade. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated daily during the outage.
 Thu 10/10/2024Mon 10/14/2024Utah County, UtahSalt Lake"A" Line Pipe Replacement Project TBDTBDNoKern River is executing a pipeline replacement project on a pipeline segment between the Salt Lake and Elberta compressor stations to comply with a class location change. Capacity is subject to change based on flow patterns at the time of the work.
 Tue 10/15/2024Thu 10/17/2024Goodsprings Compressor StationGoodspringsUnit #1 ExchangeTBDTBDNoUnits two and three of the station will be available during the exchange of unit one. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage.
 Mon 10/21/2024Fri 10/25/2024Dry Lake Compressor StationDry LakeUnit Seal Gas ProjectTBDTBDNoDry Lake compressor station will be out of service for the duration of the work. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
NewMon 10/28/2024Fri 11/01/2024Salt Lake Compressor StationSalt LakeCompressor Seal UpgradesTBDTBDNoOne of the two units will be available for the duration of the project. Impact to capacity is subject to change based on the flow patterns at the time. Capacity will be updated for each cycle during the outage.
Customer nominations will be scheduled pursuant to Section 13 of the General Terms and Conditions of Kern River's FERC Gas Tariff.