Planned Service Outage
TSP NameTSP DUNSPost DatePost Time
KERN RIVER GAS TRANSMISSION COMPANY 621617372 01/21/2025 19:27:27

Notice TypePosted
Date/Time
Notice Effective
Date/Time
Notice End
Date/Time
Notice
Identifier
SubjectResponse
Date/Time
Notice
Status
Prior
Notice
Identifier
         

There are no Planned Service Outages in effect.
Notice Status Key:
1 = Initiate
2 = Supersede
3 = Terminate

 

Planned Service Outage - Maintenance Schedule


TSP NameTSP DUNSPost DatePost Time
KERN RIVER GAS TRANSMISSION COMPANY 621617372 01/21/2025 19:27:27

StatusStart DateEnd DateLocation NameCapacity
Reduction
Location
Work to be
Performed
Estimated
Operational
Capacity Dth
Estimated
Operational
Capacity
Reduction Dth
Anticipated
Impact
to Firm
Nominations
Additional Information
ChangedWed 02/19/2025Wed 02/19/2025Milford Compressor StationMilfordAnnual Emergency Shutdown (ESD) Test 2,419,000 67,000NoMilford compressor station will be out of service for 10 hours while the annual ESD Test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
ChangedThu 02/20/2025Thu 02/20/2025Milford Compressor StationMilfordAnnual Unit Maintenance 2,326,000 160,000NoMilford compressor station will be out of service during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
ChangedTue 02/25/2025Tue 02/25/2025Salt Lake Compressor StationSalt LakeAnnual Emergency Shutdown (ESD) Test 2,297,000 38,000NoSalt Lake compressor station will be out of service for 10 hours while the annual ESD Test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
ChangedTue 02/25/2025Wed 02/26/2025Dry Lake Compressor StationDry LakeAnnual Unit Maintenance 2,354,000 99,000NoOne of the two units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
ChangedWed 02/26/2025Thu 02/27/2025Salt Lake Compressor StationSalt LakeAnnual Unit Maintenance 2,291,000 44,000NoOne of the two units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
ChangedThu 02/27/2025Thu 02/27/2025Dry Lake Compressor StationDry LakeAnnual Emergency Shutdown (ESD) Test 2,373,000 80,000NoDry Lake compressor station will be out of service for 10 hours while the ESD test is performed. Capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
ChangedTue 03/04/2025Tue 03/04/2025Fillmore Compressor StationFillmoreAnnual Emergency Shutdown (ESD) Test 2,364,000 96,000NoFillmore compressor station will be out of service for 10 hours while the annual ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
ChangedWed 03/05/2025Thu 03/06/2025Fillmore Compressor StationFillmoreAnnual Unit Maintenance 2,329,000 131,000NoOne of the two units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the work.
ChangedMon 03/17/2025Mon 03/17/2025Goodsprings Compressor StationGoodspringsAnnual Emergency Shutdown (ESD) Test 1,736,000 258,000NoGoodsprings compressor station will be out of service for 12 hours while the annual ESD Test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
ChangedTue 03/18/2025Thu 03/20/2025Goodsprings Compressor StationGoodspringsAnnual Unit Maintenance 1,844,000 150,000NoTwo of the three units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
ChangedTue 03/25/2025Tue 03/25/2025Veyo Compressor StationVeyoAnnual Emergency Shutdown (ESD) Test 2,310,000 125,000NoVeyo compressor station will be out of service for 12 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
ChangedTue 03/25/2025Wed 03/26/2025Painter Compressor StationPainter PlantAnnual Unit Maintenance 185,000 89,400NoOne of the two units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
ChangedWed 03/26/2025Fri 03/28/2025Veyo Compressor StationVeyoAnnual Unit Maintenance 2,353,000 82,000NoTwo of the three units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
 Mon 04/07/2025Fri 04/11/2025Milford Compressor StationMilfordUnit Engine ExchangeTBDTBDNoMilford station will be out of service for the duration of the engine exchange. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
 Tue 04/15/2025Tue 04/15/2025Muddy Creek "A" Compressor StationMuddy CreekAnnual Emergency Shutdown (ESD) TestTBDTBDNoMuddy Creek "A" plant will be out of service for 12 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
 Thu 04/17/2025Fri 04/25/2025Veyo Compressor StationVeyoVeyo Unit #2 Controls UpgradeTBDTBDNoUnits #1 and #3 will be available for the duration of the unit #2 controls upgrade. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated daily during the outage.
 Tue 04/29/2025Tue 04/29/2025Elberta Compressor StationElbertaAnnual Emergency Shutdown (ESD) TestTBDTBDNoElberta compressor station will be out of service for 10 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
 Tue 04/29/2025Thu 05/01/2025Muddy Creek "A" Compressor StationMuddy CreekAnnual Unit MaintenanceTBDTBDNoTwo of the three units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
 Wed 04/30/2025Thu 05/01/2025Elberta Compressor StationElbertaAnnual Unit MaintenanceTBDTBDNoOne of the two units will be available during the maintenance. Impact to capacity is subject to change based on the flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
 Tue 05/06/2025Wed 05/07/2025Muddy Creek "B" Compressor StationMuddy CreekAnnual Unit MaintenanceTBDTBDNoTwo of the three units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
 Thu 05/08/2025Thu 05/08/2025Muddy Creek "B" Compressor StationMuddy CreekUnit #6 Annual MaintenanceTBDTBDNoUnits #4 and #5 will be available during the maintenance of unit #6. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
 Wed 05/14/2025Wed 05/14/2025Muddy Creek "B" Compressor StationMuddy CreekAnnual Emergency Shutdown (ESD) TestTBDTBDNoMuddy Creek "B" plant will be out of service for 12 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
 Tue 05/20/2025Wed 05/21/2025Coyote Creek Compressor StationCoyote CreekAnnual Unit MaintenanceTBDTBDNoOne of the two units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
 Thu 05/22/2025Thu 05/22/2025Coyote Creek Compressor StationCoyote CreekAnnual Emergency Shutdown (ESD) TestTBDTBDNoCoyote Creek compressor station will be out of service for 10 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
 Tue 05/27/2025Tue 05/27/2025Painter Compressor StationPainter PlantAnnual Emergency Shutdown (ESD) TestTBDTBDNoThe Painter compressor station will out of service for 10 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
ChangedThu 10/02/2025Fri 10/10/2025Muddy Creek "B" Compressor StationMuddy CreekMuddy Creek Unit #4 Controls UpgradeTBDTBDNoUnits #5 and #6 will be available for the duration of the unit #4 controls upgrade. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated daily during the outage.
 Mon 11/03/2025Fri 11/07/2025Elberta Compressor StationElbertaCompressor Seal Gas ProjectTBDTBDNoElberta compressor station will be out of service for the duration of the work. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
Customer nominations will be scheduled pursuant to Section 13 of the General Terms and Conditions of Kern River's FERC Gas Tariff.