TSP NameTSP DUNSPost DatePost Time
KERN RIVER GAS TRANSMISSION COMPANY 621617372 04/28/2024 09:58:04

Notice TypePosted
Date/Time
Notice Effective
Date/Time
Notice End
Date/Time
Notice
Identifier
SubjectResponse
Date/Time
Notice
Status
Prior
Notice
Identifier
         

There are no Planned Service Outages in effect.
Notice Status Key:
1 = Initiate
2 = Supersede
3 = Terminate

 

Planned Service Outage - Maintenance Schedule


TSP NameTSP DUNSPost DatePost Time
KERN RIVER GAS TRANSMISSION COMPANY 621617372 04/28/2024 09:58:04

StatusStart DateEnd DateLocation NameCapacity
Reduction
Location
Work to be
Performed
Estimated
Operational
Capacity Dth
Estimated
Operational
Capacity
Reduction Dth
Anticipated
Impact
to Firm
Nominations
Additional Information
 Thu 03/07/2024Fri 05/31/2024Centennial Meter StationCentennial - SW GasLine Replacement 209,000 209,000NoThe Centennial meter station will be out of service for the duration of the project.
 Tue 04/30/2024Thu 05/02/2024Muddy Creek "B" Compressor StationMuddy CreekUnit #6 Exchange 1,887,000 238,000NoUnits four and five of the "B" plant will be available during the exchange of unit six. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage.
ChangedMon 05/06/2024Tue 05/07/2024Muddy Creek "B" Compressor StationMuddy CreekAnnual Unit Maintenance 1,947,000 100,000NoTwo of the three units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
ChangedTue 05/07/2024Tue 05/07/2024Elberta Compressor StationElbertaAnnual Emergency Shutdown (ESD) Test 2,294,000 83,000NoElberta compressor station will be out of service for 10 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage
ChangedWed 05/08/2024Thu 05/09/2024Elberta Compressor StationElbertaAnnual Unit Maintenance 2,252,000 125,000NoOne of the two units will be available during the maintenance. Impact to capacity is subject to change based on the flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
ChangedFri 05/10/2024Fri 05/10/2024Muddy Creek "B" Compressor StationMuddy CreekUnit #6 Annual Maintenance 1,840,000 207,000NoUnits #4 and #5 will be available during the maintenance of unit #6. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
ChangedTue 05/14/2024Wed 05/15/2024Coyote Creek Compressor StationCoyote CreekAnnual Unit Maintenance 2,123,000 28,000NoOne of the two units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
ChangedThu 05/16/2024Thu 05/16/2024Coyote Creek Compressor StationCoyote CreekAnnual Emergency Shutdown (ESD) Test 2,113,000 38,000NoCoyote Creek compressor station will be out of service for 10 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
CanceledTue 05/21/2024Fri 05/24/2024Veyo Compressor StationVeyoUnit #3 Compressor ExchangeTBDTBDNoUnits one and two will be available during the compressor exchange of unit three. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage.
CanceledMon 05/27/2024Tue 06/11/2024Riverton Meter StationRiverton - Questar GasStrength TestTBDTBDNoThe Riverton meter station will be out of service for the duration of the project.
ChangedTue 05/28/2024Tue 05/28/2024Painter Compressor StationPainter PlantAnnual Emergency Shutdown (ESD) Test 160,000 114,400NoThe Painter compressor station will out of service for 10 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage.
 Wed 10/02/2024Thu 10/10/2024Muddy Creek "A" Compressor StationMuddy CreekUnit #3 Controls UpgradeTBDTBDNoUnit one and two will be available for the duration of the unit #3 controls upgrade. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated daily during the outage.
NewThu 10/10/2024Mon 10/14/2024Utah County, UtahSalt Lake"A" Line Pipe Replacement Project TBDTBDNoKern River is executing a pipeline replacement project on a pipeline segment between the Salt Lake and Elberta compressor stations to comply with a class location change. Capacity is subject to change based on flow patterns at the time of the work.
ChangedTue 10/15/2024Thu 10/17/2024Goodsprings Compressor StationGoodspringsUnit #1 ExchangeTBDTBDNoUnits two and three of the station will be available during the exchange of unit one. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage.
ChangedMon 10/21/2024Fri 10/25/2024Dry Lake Compressor StationDry LakeUnit Seal Gas ProjectTBDTBDNoDry Lake compressor station will be out of service for the duration of the work. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage.
Customer nominations will be scheduled pursuant to Section 13 of the General Terms and Conditions of Kern River's FERC Gas Tariff.