| Tue 02/07/2023 | Thu 02/09/2023 | Milford Compressor Station | Milford | Compressor Seal Gas Project | 2,377,000 | 133,000 | No | Milford compressor station will be out of service for the duration of the work. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage. |
New | Wed 02/15/2023 | Wed 02/15/2023 | Painter Compressor Station | Painter Plant | Lube Oil System Maintenance | 251,500 | 47,500 | No | One of the two units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage. |
| Wed 02/22/2023 | Wed 02/22/2023 | Milford Compressor Station | Milford | Annual Emergency Shutdown (ESD) Test | 2,454,583 | 55,417 | No | Milford compressor station will be out of service for 10 hours while the annual ESD Test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage. |
| Thu 02/23/2023 | Thu 02/23/2023 | Milford Compressor Station | Milford | Annual Unit Maintenance | 2,377,000 | 133,000 | No | The station will be out of service during the maintenance. Impact to capacity is subject to be changed based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage. |
| Tue 02/28/2023 | Tue 02/28/2023 | Salt Lake Compressor Station | Salt Lake | Annual Emergency Shutdown (ESD) Test | 2,285,583 | 35,417 | No | Salt Lake compressor station will be out of service for 10 hours while the annual ESD Test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage. |
Changed | Wed 03/01/2023 | Thu 03/02/2023 | Salt Lake Compressor Station | Salt Lake | Annual Unit Maintenance | 2,252,000 | 30,000 | No | One of the two units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage. |
Changed | Tue 03/07/2023 | Tue 03/07/2023 | Fillmore Compressor Station | Fillmore | Annual Emergency Shutdown (ESD) Test | 2,392,000 | 93,000 | No | Fillmore compressor station will be out of service for 10 hours while the annual ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage. |
Changed | Tue 03/07/2023 | Thu 03/09/2023 | Salt Lake Compressor Station | Salt Lake | Unit #1 Exchange | 2,252,000 | 30,000 | No | Unit two will be available during the exchange of unit one. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage. |
Changed | Wed 03/08/2023 | Thu 03/09/2023 | Fillmore Compressor Station | Fillmore | Annual Unit Maintenance | 2,366,000 | 119,000 | No | One of the two units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the work. |
Changed | Tue 03/14/2023 | Wed 03/15/2023 | Dry Lake Compressor Station | Dry Lake | Annual Unit Maintenance | 2,307,000 | 155,000 | No | One of the two units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated each scheduling cycle during the outage. |
Changed | Tue 03/14/2023 | Wed 03/15/2023 | Painter Compressor Station | Painter Plant | Annual Unit Maintenance | 185,000 | 89,400 | No | One of the two units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage. |
Changed | Thu 03/16/2023 | Thu 03/16/2023 | Dry Lake Compressor Station | Dry Lake | Annual Emergency Shutdown (ESD) Test | 2,354,000 | 108,000 | No | Dry Lake compressor station will be out of service for 10 hours while the ESD test is performed. Capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage. |
Changed | Thu 03/16/2023 | Thu 03/16/2023 | Painter Compressor Station | Painter Plant | Annual Emergency Shutdown (ESD) Test | 160,000 | 114,400 | No | The Painter compressor station will out of service for 10 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage. |
Changed | Tue 03/21/2023 | Tue 03/21/2023 | Goodsprings Compressor Station | Goodsprings | Annual Emergency Shutdown (ESD) Test | 1,736,500 | 228,500 | No | Goodsprings compressor station will be out of service for 12 hours while the annual ESD Test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage. |
Changed | Tue 03/21/2023 | Thu 03/23/2023 | Muddy Creek "A" Plant | Muddy Creek | Unit #1 Exchange | 2,014,000 | 146,000 | No | Units two and three of the "A" plant will be available during the exchange of unit one. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage. |
Changed | Wed 03/22/2023 | Fri 03/24/2023 | Goodsprings Compressor Station | Goodsprings | Annual Unit Maintenance | 1,818,000 | 184,000 | No | Two of the three units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage. |
| Tue 03/28/2023 | Wed 03/29/2023 | Coyote Creek Compressor Station | Coyote Creek | Annual Unit Maintenance | TBD | TBD | No | One of the two units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage. |
| Tue 03/28/2023 | Thu 03/30/2023 | Veyo Compressor Station | Veyo | Unit #3 Exchange | TBD | TBD | No | Units one and two will be available during the exchange of unit three. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage. |
| Thu 03/30/2023 | Thu 03/30/2023 | Coyote Creek Compressor Station | Coyote Creek | Annual Emergency Shutdown (ESD) Test | TBD | TBD | No | Coyote Creek compressor station will be out of service for 10 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage. |
| Tue 04/04/2023 | Tue 04/04/2023 | Veyo Compressor Station | Veyo | Annual Emergency Shutdown (ESD) Test | TBD | TBD | No | Veyo compressor station will be out of service for 12 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage. |
| Tue 04/04/2023 | Thu 04/06/2023 | Coyote Creek Compressor Station | Coyote Creek | Unit #1 Exchange | TBD | TBD | No | Unit two will be available during the exchange of unit one. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage. |
| Sat 04/08/2023 | Sun 05/07/2023 | Utah County, Utah | Salt Lake | "A" Line Pipe Replacement Project | TBD | TBD | No | Kern River is executing a pipeline replacement project on a pipeline segment between the Salt Lake and Elberta compressor stations to comply with a class location change. Capacity is subject to change based on flow patterns at the time of the work. |
| Wed 04/12/2023 | Wed 04/12/2023 | Muddy "A" Creek Compressor Station | Muddy Creek | Annual Emergency Shutdown (ESD) Test | TBD | TBD | No | Muddy Creek "A" plant will be out of service for 12 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage. |
| Wed 04/12/2023 | Fri 04/14/2023 | Veyo Compressor Station | Veyo | Annual Unit Maintenance | TBD | TBD | No | Two of the three units will available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage. |
| Wed 04/19/2023 | Wed 04/19/2023 | Muddy Creek "B" Compressor Station | Muddy Creek | Annual Emergency Shutdown (ESD) Test | TBD | TBD | No | Muddy Creek "B" plant will be out of service for 12 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage. |
| Thu 04/20/2023 | Fri 04/28/2023 | Elberta Compressor Station | Elberta | Elberta Unit #1 Controls Upgrades | TBD | TBD | No | Unit two will be available for the duration of the controls upgrade. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated daily during the outage. |
| Tue 05/02/2023 | Thu 05/04/2023 | Muddy Creek "A" Compressor Station | Muddy Creek | Annual Unit Maintenance | TBD | TBD | No | Two of the three units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage. |
| Tue 05/09/2023 | Tue 05/09/2023 | Elberta Compressor Station | Elberta | Annual Emergency Shutdown (ESD) Test | TBD | TBD | No | Elberta compressor station will be out of service for 10 hours while the ESD test is performed. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated prior to the outage |
| Tue 05/09/2023 | Thu 05/11/2023 | Muddy Creek "B" Compressor Station | Muddy Creek | Annual Unit Maintenance | TBD | TBD | No | Two of the three units will be available during the maintenance. Impact to capacity is subject to change based on flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage. |
| Wed 05/10/2023 | Thu 05/11/2023 | Elberta Compressor Station | Elberta | Annual Unit Maintenance | TBD | TBD | No | One of the two units will be available during the maintenance. Impact to capacity is subject to change based on the flow patterns at the time of the work. Capacity will be updated for each scheduling cycle during the outage. |
| Sat 05/13/2023 | Sun 05/28/2023 | Salt Lake County, Utah | Salt Lake | "B" Line Strength Test | TBD | TBD | No | Kern River is executing a pipeline strength test project for a pipeline segment between the Salt Lake and Elberta compressor stations to comply with a class location change. Capacity is subject to change based on flow patterns at the time of the work. |
| Tue 05/16/2023 | Thu 05/18/2023 | Coyote Creek Compressor Station | Coyote Creek | Unit #2 Exchange | TBD | TBD | No | Unit one will be available during the exchange of unit two. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage. |
| Sat 06/03/2023 | Mon 06/19/2023 | Davis County, Utah | Coyote Creek | "A" Line Strength Test | TBD | TBD | No | Kern River is executing a pipeline strength test project for a pipeline segment between the Coyote Creek and Salt Lake compressor stations to comply with a class location change. Capacity is subject to change based on flow patterns at the time of the work. |
| Tue 09/19/2023 | Thu 09/21/2023 | Salt Lake Compressor Station | Salt Lake | Unit #2 Exchange | TBD | TBD | No | Units one will be available during the exchange of unit two. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage. |
| Tue 10/03/2023 | Thu 10/05/2023 | Muddy Creek "B" Compressor Station | Muddy Creek | Unit #2 Exchange | TBD | TBD | No | Units one and three will be available during the exchange of unit two. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage. |
| Tue 10/10/2023 | Thu 10/12/2023 | Elberta Compressor Station | Elberta | Unit #1 Exchange | TBD | TBD | No | Unit two will be available during the exchange of unit one. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage. |
| Tue 10/24/2023 | Thu 10/26/2023 | Dry Lake Compressor Station | Dry Lake | Unit #2 Exchange | TBD | TBD | No | Unit one will be available during the exchange of unit two. Impact to capacity is subject to change based on flow patterns at the time of the exchange. Capacity will be updated for each scheduling cycle during the outage. |