Informational Postings
Notices
Planned Service Outage
TSP NameTSP DUNSPost DatePost Time
KERN RIVER GAS TRANSMISSION COMPANY 621617372 04/18/2019 18:24:42

Notice TypePosted
Date/Time
Notice Effective
Date/Time
Notice End
Date/Time
Notice
Identifier
SubjectResponse
Date/Time
Notice
Status
Prior
Notice
Identifier
 Maint03/27/2019 12:0703/27/2019 12:0704/27/2019 12:0720190219 Kern River - Update to Maintenance Schedule  N/A 2 20190135
 Maint03/09/2019 07:1803/09/2019 07:1803/10/2019 07:1820190180 Kern River - Dry Lake Compressor Station Maintenance Completed Early  N/A 1 
 Maint03/06/2019 12:3603/06/2019 12:3603/07/2019 12:3620190170 Kern River - Rapids System and Website Maintenance  N/A 1 
 Maint03/01/2019 12:2703/01/2019 12:2703/09/2019 12:2720190160 Kern River - Scheduled Maintenance Reminder  N/A 1 
 Maint02/21/2019 07:0702/21/2019 07:0702/23/2019 07:0720190137 Kern River - Compressor Station Maintenance Postponed  N/A 1 
 Maint02/20/2019 16:5202/20/2019 16:5203/22/2019 16:5220190135 Kern River - Update to Maintenance Schedule  N/A 3 20190064
 Maint02/18/2019 11:3102/18/2019 11:3102/23/2019 11:3120190122 Kern River - Scheduled Maintenance Reminder  N/A 1 
 Maint02/08/2019 17:5802/08/2019 17:5802/16/2019 09:0020190099 Kern River - Scheduled Maintenance Reminder  N/A 1 
 Maint01/24/2019 16:5101/24/2019 16:5101/25/2019 16:5120190064 Kern River - Update to Maintenance Schedule  N/A 3 20190054
 Maint01/21/2019 15:0201/21/2019 15:0201/28/2019 15:0220190054 Kern River - Update to Maintenance Schedule  N/A 3 20180900


Notice Status Key:
1 = Initiate
2 = Supersede
3 = Terminate

Planned Service Outage - Maintenance Schedule

TSP NameTSP DUNSPost DatePost Time
KERN RIVER GAS TRANSMISSION COMPANY 621617372 04/18/2019 18:24:42

StatusStart DateEnd DateLocation NameCapacity
Reduction
Location
Work to be
Performed
Estimated
Operational
Capacity Dth
Estimated
Operational
Capacity
Reduction Dth
Anticipated
Impact
to Firm
Nominations
Additional Information
ChangedTue 04/23/2019Tue 04/23/2019Muddy Creek A Compressor StationMuddy CreekAnnual Emergency Shutdown (ESD) Test 1,814,000 414,000NoMuddy Creek A compressor station will be out of service for 12 hours while the annual ESD Test is performed.
ChangedThu 04/25/2019Thu 04/25/2019Muddy Creek B Compressor StationMuddy CreekAnnual Emergency Shutdown (ESD) Test 1,771,000 457,000NoMuddy Creek B compressor station will be out of service for 12 hours while the annual ESD Test is performed
ChangedSun 05/12/2019Sat 05/18/2019Veyo Compressor StationVeyoVeyo Station Controls Upgrade 2,225,000 156,000NoVeyo compressor station will be out of service for the duration of the station controls upgrade.
 Sun 09/22/2019Sat 09/28/2019Painter Compressor StationPainter PlantPainter Station Controls UpgradeTBDTBDNoPainter compressor station will be out of service for the duration of the station controls upgrade.
 Tue 10/08/2019Thu 10/10/2019Muddy Creek Compressor StationMuddy CreekUnit #6 ExchangeTBDTBDNoFive of the six units will be available during the maintenance
Customer nominations will be scheduled pursuant to Section 13 of the General Terms and Conditions of Kern River's FERC Gas Tariff.