Informational Postings
Notices
Planned Service Outage
TSP NameTSP DUNSPost DatePost Time
KERN RIVER GAS TRANSMISSION COMPANY 621617372 10/19/2017 09:49:23

Notice TypePosted
Date/Time
Notice Effective
Date/Time
Notice End
Date/Time
Notice
Identifier
SubjectResponse
Date/Time
Notice
Status
Prior
Notice
Identifier
 Maint09/21/2017 17:1909/21/2017 17:1910/31/2017 16:4720170546 Subject: Kern River- Update to Maintenance Schedule  N/A 1 
 Maint09/20/2017 15:1509/20/2017 15:1512/31/2017 14:3420170541 Kern River - Updated 2017 Maintenance Calendar  N/A 2 20170446
 Maint08/16/2017 14:5308/16/2017 14:5309/30/2017 14:0420170446 Kern River - Updated 2017 Maintenance Calendar  N/A 3 20170388
 Maint07/20/2017 15:1207/20/2017 15:1209/02/2017 13:4020170388 Kern River - Updated 2017 Maintenance Calendar  N/A 3 20170327
 Maint06/16/2017 16:3606/16/2017 16:3612/31/2017 16:3620170327 Kern River - Updated 2017 Maintenance Calendar  N/A 3 20170326
 Maint06/16/2017 15:0706/16/2017 15:0712/31/2017 14:3320170326 Kern River - Updated 2017 Maintenance Calendar  N/A 3 20170275


Notice Status Key:
1 = Initiate
2 = Supersede
3 = Terminate

Planned Service Outage - Maintenance Schedule

TSP NameTSP DUNSPost DatePost Time
KERN RIVER GAS TRANSMISSION COMPANY 621617372 10/19/2017 09:49:24

New or
Changed
Start DateEnd DateLocation NameCapacity
Reduction
Location
Work to be
Performed
Estimated
Operational
Capacity Dth
Estimated
Operational
Capacity
Reduction Dth
Anticipated
Impact
to Firm
Nominations
Additional Information
 Mon 10/16/2017Thu 10/19/2017Salt Lake Compressor Station Unit #2VeyoDischarge Valve Replacement2,344,000112,000No 
 Mon 10/23/2017Tue 10/31/2017Coyote Creek Compressor StationCoyote CreekStation Control Upgrade2,139,000161,000No 
 Wed 11/01/2017Mon 11/06/2017Coyote Creek Compressor StationCoyote CreekStation Control Upgrade2,222,000124,000No 
 Mon 11/06/2017Thu 11/09/2017Veyo Compressor Station Unit #2VeyoDischarge Valve Replacement2,201,000255,000No 
ChangedTue 11/14/2017Thu 11/16/2017Veyo Compressor Station Unit #1VeyoTurbine Exchange2,426,00030,000NoDates Changed from September 26-28 2017
ChangedTue 11/14/2017Thu 11/16/2017Elberta Compressor Station Unit #1VeyoTurbine ExchangeN/AN/ANoCompleted ahead of schedule
Customer nominations will be scheduled pursuant to Section 13 of the General Terms and Conditions of Kern River's FERC Gas Tariff.