TSP NameTSP DUNSPost DatePost Time
KERN RIVER GAS TRANSMISSION COMPANY 621617372 02/19/2018 19:26:36

Notice TypePosted
Date/Time
Notice Effective
Date/Time
Notice End
Date/Time
Notice
Identifier
SubjectResponse
Date/Time
Notice
Status
Prior
Notice
Identifier
 Maint02/19/2018 11:2302/19/2018 11:2302/25/2018 11:2320180124 Kern River - Dry Lake Compressor Station Maintenance Postponed  N/A 1 
 Maint02/16/2018 18:1302/16/2018 18:1302/28/2018 18:1320180120 Kern River - Update to Maintenance Schedule  N/A 2 20180109
 Maint02/13/2018 09:0902/13/2018 09:0903/20/2018 09:0920180109 Kern River - Update to Maintenance Schedule  N/A 3 20180092
 Maint02/05/2018 15:0402/05/2018 15:0403/05/2018 15:0420180092 Kern River - Update to Maintenance Schedule  N/A 3 20180054
 Maint01/19/2018 16:5601/19/2018 16:5602/21/2018 16:5620180054 Kern River - Update to Maintenance Schedule  N/A 3 20170764
 Maint12/20/2017 17:5312/20/2017 17:5301/22/2018 17:5320170764 Kern River - Update to Maintenance Schedule  N/A 3 20170681
 Maint06/16/2017 16:3606/16/2017 16:3612/31/2017 16:3620170327 Kern River - Updated 2017 Maintenance Calendar  N/A 3 20170326


Notice Status Key:
1 = Initiate
2 = Supersede
3 = Terminate

Planned Service Outage - Maintenance Schedule

TSP NameTSP DUNSPost DatePost Time
KERN RIVER GAS TRANSMISSION COMPANY 621617372 02/19/2018 19:26:37

StatusStart DateEnd DateLocation NameCapacity
Reduction
Location
Work to be
Performed
Estimated
Operational
Capacity Dth
Estimated
Operational
Capacity
Reduction Dth
Anticipated
Impact
to Firm
Nominations
Additional Information
CompletedTue 02/20/2018Thu 02/22/2018Muddy Creek "B" Compressor StationMuddy CreekAnnual Unit Maintenance 2,071,000 194,000NoTwo of the three units will be available during the maintenance.
ChangedTue 02/20/2018Tue 02/20/2018Dry Lake Compressor StationVeyoAnnual ESD Test 2,306,000 194,000NoDry Lake compressor station will be out of service for 10 hours while the annual ESD Test is performed.
CompletedWed 02/21/2018Thu 02/22/2018Dry Lake Compressor StationVeyoAnnual Unit Maintenance 2,306,000 194,000NoOne of the two units will be available during the maintenance.
ChangedTue 02/27/2018Wed 02/28/2018Fillmore Compressor StationVeyoAnnual Unit Maintenance 2,297,000 203,000NoOne of the two units will be available during the maintenance.
CompletedThu 03/01/2018Thu 03/01/2018Fillmore Compressor StationVeyoAnnual ESD Test 2,371,000 68,000NoFillmore compressor station will be out of service for 10 hours while the annual ESD Test is performed.
CompletedTue 02/27/2018Wed 02/28/2018Muddy Creek "A" Compressor StationMuddy CreekAnnual Unit Maintenance 2,062,000 203,000NoThis work has been completed ahead of schedule.
ChangedTue 03/06/2018Tue 03/06/2018Painter Compressor StationPainter PlantAnnual ESD Test 206,000 68,000NoPainter compressor station will be out of service for 10 hours while the annual ESD Test is performed.
ChangedWed 03/07/2018Thu 03/08/2018Painter Compressor StationPainter PlantAnnual Unit Maintenance 206,000 68,000NoOne of the two units will be available during the maintenance.
ChangedTue 03/06/2018Tue 03/06/2018Salt Lake Compressor StationVeyoAnnual ESD Test 2,378,000 61,000NoSalt Lake compressor station will be out of service for 10 hours while the annual ESD Test is performed.
CompletedWed 03/07/2018Thu 03/08/2018Salt Lake Compressor StationVeyoAnnual Unit Maintenance 2,393,000 46,000NoThis work has been completed ahead of schedule.
ChangedTue 03/13/2018Thu 03/15/2018Veyo Compressor StationVeyoUnit #3 Exchange 2,409,000 30,000NoTwo of the three units will be available during the unit #3 exchange.
ChangedTue 04/17/2018Thu 04/19/2018Muddy Creek Compressor StationMuddy CreekUnit #1 Exchange 2,084,000 180,000NoTwo of the three units will be available during the unit #1 exchange.
ChangedTue 03/27/2018Wed 03/28/2018Elberta Compressor StationVeyoAnnual Unit Maintenance 2,196,000 243,000NoOne of the two units will be available during the maintenance.
ChangedTue 03/27/2018Tue 03/27/2018Goodsprings Compressor StationGoodspringsAnnual ESD Test 1,720,000 243,000NoGoodsprings compressor station will be out of service for 12 hours while the annual ESD Test is performed.
CompletedWed 03/28/2018Wed 03/28/2018Goodsprings Compressor StationGoodspringsAnnual Unit Maintenance 1,893,000 71,000NoThis work has been completed ahead of schedule.
ChangedTue 04/03/2018Wed 04/04/2018Coyote Creek Compressor StationVeyoAnnual Unit Maintenance 2,385,000 72,000NoOne of the two units will be available during the maintenance.
ChangedThu 04/05/2018Thu 04/05/2018Coyote Creek Compressor StationVeyoAnnual ESD Test 2,402,000 55,000NoCoyote Creek compressor station will be out of service for 10 hours while the annual ESD Test is performed.
ChangedMon 04/09/2018Tue 04/17/2018Elberta Compressor StationVeyoStation Controls Upgrade 2,290,000 167,000NoElberta compressor station will be out of service for the duration of the station controls upgrade.
CompletedTue 04/24/2018Tue 04/24/2018Milford Compressor Station VeyoAnnual ESD Test NoThis work has been completed ahead of schedule.
CompletedWed 04/25/2018Thu 04/26/2018Milford Compressor StationVeyoAnnual Unit MaintenanceTBDTBDNoThis work has been completed ahead of schedule
 Thu 05/03/2018Thu 05/03/2018Muddy Creek "A" Compressor StationMuddy CreekAnnual ESD TestTBDTBDNoMuddy Creek "A" compressor station will be out of service for 12 hours while the annual ESD Test is performed.
 Thu 05/10/2018Thu 05/10/2018Muddy Creek "B" Compressor StationMuddy CreekAnnual ESD TestTBDTBDNoMuddy Creek "B" compressor station will be out of service for 12 hours while the annual ESD Test is performed.
 Tue 09/11/2018Thu 09/13/2018Fillmore Compressor StationVeyoUnit #1 ExchangeTBDTBDNoUnit #2 will be available during the exchange of unit #1.
 Fri 09/14/2018Sun 09/23/2018Dry Lake Compressor StationVeyoStation Controls UpgradeTBDTBDNoDry Lake compressor station will be out of service for the duration of the station controls upgrade.
 Fri 10/19/2018Sun 10/28/2018Fillmore Compressor StationVeyoStation Controls UpgradeTBDTBDNoFillmore compressor station will be out of service for the duration of the station controls upgrade.
 Tue 11/06/2018Thu 11/08/2018Goodsprings Compressor StationGoodspringsUnit #1 ExchangeTBDTBDNoTwo of the three units will be available during the unit #3 exchange.
Customer nominations will be scheduled pursuant to Section 13 of the General Terms and Conditions of Kern River's FERC Gas Tariff.