Informational Postings
Informational Postings
Daily Operational Report
Monday, February 19, 2018 7:10 PM CCT
Direct Connected Delivery Points Solely Served by Kern River
Meter NumberMeter NameState
024015Harry Allen - NV EnergyNEVADA
024023Arrolime - SCPPANEVADA
024024Moapa - NV EnergyNEVADA
024025Bighorn - NV EnergyNEVADA
Meter NumberMeter NameState
024027Silverhawk - NV EnergyNEVADA
024028Mountain Pass - Molycorp MineralsCALIFORNIA
024033Reid Gardner - NV EnergyNEVADA
024034Ivanpah - Solar PartnersCALIFORNIA
Pipeline Conditions & Balancing Guidelines
Line pack on Kern River's system is normal. Colder temperatures are forecasted in Kern River's Market area through February 21, 2018, and maintenance at the Dry Lake compressor station is scheduled on February 20, 2018. Therefore, Kern River requests that all shippers and operators align daily scheduled nominations and confirmations with physical receipts and deliveries to be on rate. Please contact your Marketing and Customer Services representative or the Customer Services hotline at 801-937-6111 in advance for any balancing arrangements.
System Line Pack

Graph is only representative of the line pack in Kern River's wholly owned system from the Opal receipt meter to the Daggett compressor station, and does not include the line pack in the Kern River/Mojave co-owned system from the Daggett compressor station to the end of the east and west-side laterals ("Common Facilities") or the line pack in Kern River's wholly owned High Desert lateral.

Notices
Today's Schedulers
AM: Jana Stewart
PM: Ryan Jones
Hotline: (801) 937-6111
Email: krsched@kernrivergas.com
Transportation Sales Contacts
Contact: BRETT MAYLETT
Office: (801) 937-6210
Cell: (801) 599-4208
Email: brett.maylett@kernrivergas.com
IM: ICE Chat-Brett Maylett
Contact: DAN ROBBINS
Office: (801) 937-6167
Cell: (801) 971-9704
Email: Daniel.Robbins@kernrivergas.com
IM: ICE Chat-Dan Robbins
Operationally Available Capacity

Kern River considers line pack and operating conditions in all segments of the system, including Kern River's wholly-owned mainline and the Kern River/Mojave Common Facilities, when operationally available capacities at mainline compressors are determined.

Muddy Creek Compressor (054001)
Eff Gas DayCycleOperating CapacityKern Total Scheduled QuantityMojave Total Scheduled QuantityOperationally Available Capacity
02/20/2018 TIM 2,300,000 2,066,960 0 233,040
02/19/2018 ID2 2,300,000 2,083,778 0 216,222
02/18/2018 ID3 2,300,000 1,906,639 0 393,361
Painter Plant Compressor (054012)
Eff Gas DayCycleOperating CapacityKern Total Scheduled QuantityMojave Total Scheduled QuantityOperationally Available Capacity
02/20/2018 TIM 299,000 47,960 0 251,040
02/19/2018 ID2 299,000 47,960 0 251,040
02/18/2018 ID3 299,000 45,113 0 253,887
Coyote Creek Compressor (054023)
Eff Gas DayCycleOperating CapacityKern Total Scheduled QuantityMojave Total Scheduled QuantityOperationally Available Capacity
02/20/2018 TIM 2,400,000 2,114,920 0 285,080
02/19/2018 ID2 2,400,000 2,131,738 0 268,262
02/18/2018 ID3 2,400,000 1,951,752 0 448,248
Veyo Compressor (054015)
Eff Gas DayCycleOperating CapacityKern Total Scheduled QuantityMojave Total Scheduled QuantityOperationally Available Capacity
02/20/2018 TIM 2,490,000 2,220,191 0 269,809
02/19/2018 ID2 2,490,000 2,230,714 0 259,286
02/18/2018 ID3 2,490,000 2,104,377 0 385,623
Goodsprings Compressor (054010)
Eff Gas DayCycleOperating CapacityKern Total Scheduled QuantityMojave Total Scheduled QuantityOperationally Available Capacity
02/20/2018 TIM 1,875,000 1,645,674 0 229,326
02/19/2018 ID2 2,040,000 1,598,162 0 441,838
02/18/2018 ID3 2,040,000 1,603,267 0 436,733
Daggett Compressor (054016)
Eff Gas DayCycleOperating CapacityKern Total Scheduled QuantityMojave Total Scheduled QuantityOperationally Available Capacity
02/20/2018 TIM 1,750,000 1,574,691 0 175,309
02/19/2018 ID2 1,750,000 1,528,685 0 221,315
02/18/2018 ID3 1,750,000 1,513,586 0 236,414
Daggett - PG&E (024011)
Eff Gas DayCycleOperating CapacityKern Total Scheduled QuantityMojave Total Scheduled QuantityOperationally Available Capacity
02/20/2018 TIM 393,000 4,882 0 388,118
02/19/2018 ID2 393,000 3,382 0 389,618
02/18/2018 ID3 393,000 23,741 0 369,259
Wheeler Ridge - SoCal Gas (025011)
Eff Gas DayCycleOperating CapacityKern Total Scheduled QuantityMojave Total Scheduled QuantityOperationally Available Capacity
02/20/2018 TIM 1,056,000 491,652 182,801 381,547
02/19/2018 ID2 1,056,000 459,034 187,405 409,561
02/18/2018 ID3 1,056,000 469,054 187,402 399,544
Kramer Junction - SoCal Gas (025032)
Eff Gas DayCycleOperating CapacityKern Total Scheduled QuantityMojave Total Scheduled QuantityOperationally Available Capacity
02/20/2018 TIM 729,920 536,689 137,482 55,749
02/19/2018 ID2 729,920 477,718 137,544 114,658
02/18/2018 ID3 729,920 476,303 158,599 95,018